ElectroKinetic Solutions Inc. (EKS) Provides an Update on the EKS-DT Field Demonstration

EKS is also pleased to announce the commissioning of the field demonstration of its EKS-DT process (the “Project”). This field demonstration is the culmination of seven years of technology development. Proof-of-concept was achieved through more than three years of laboratory research. Scaled-up tests were performed at the C-FER facility in Edmonton, Alberta. A built-for-purpose test cell was constructed this spring at InnoTech Alberta’s Vegreville research facility and was filled with 1,750 m3 of fine fluid tailings. EKS designed the EKS-DT installation and fabricated and deployed…

Continue reading »